Primavara Calendar Stopped Work (Covid 19)

 

Hello all, 

 

My site was shutdown on the 24-Mar-20 due to Corona virus. 

However, my subcontractors returned to site at different time. 

 

Some of them returned on 15-Jun-20, some returned on 29-Jun-20, some on 22-Jun-20 and some on 03-Aug-20. 

 

My commercial team want to see the bars discontinue at these dates for different subcontractors. I have applied all the different calenders to each subcontractors. 

How do i show the splitted between those actities?

 

For example. if the activity started the works on 01-Feb-20 but stopped on 24-Mar-20 and resumed on 15-Jun-20. How do i show the period between 24-Mar & 14-Jun-20 as blanked? (i have applied calender)

 

 

capture.png

R
Rafael Davila 👤 Member for 22 years 3 months

Be reminded that activity interruptions can be multiple prior to data date [actual interruptions] as well as after data date [planned interruptions].

miltiple-interruptions

It is essential to keep the record straight for future claims if need be.

The Performance Archive or its P6 equivalent shall give you the details for interruptions before data date while the Calendar Exceptions or its P6 equivalent shall give you the details for planned interruptions.

Image-037



Image-038

Best Regards, Rafael

Z
Zoltan Palffy 👤 Member for 16 years 11 months

put the dates in the suspend and resume function in the status tab

and go to bars click remaining work bar then bar settings and check Under Bar necking Settings check activty nonwork intervals 

Forum Sponsor

Top Posters

Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts