Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Budgeted resorses moves with data dates

1 reply [Last post]
Reza Hasheminia
User offline. Last seen 16 years 50 weeks ago. Offline
Joined: 10 Dec 2007
Posts: 7
Dear friends,
I’ve faced a serious problem during updating my project schedule, i’ve assigned nonlabour resoreces to activities and set the schedule as initial plan, after update i found the budgeted resorces moved behind the new data date, so that it’s not posible to compare budgeted and actual resources.
please advise.
Many thanks.

Replies

Gordon Blair
User offline. Last seen 6 years 42 weeks ago. Offline
Joined: 29 Jul 2005
Posts: 166
Groups: None
Have you updated the Resource % complete in the Resources Tab?