Hello Planning professionals,
When updating P6 schedule using Duration % complete, Units are not getting updated automatically. This issue exists when maintain & Assign baseline using "save a copy of project as new baseline" option is chosen. However the issue gets solved when I opted for " Convert another project to a new baseline of the current Project" option. Would like to know the root cause of the issue. Please help
Settings I used,
Project Defaults
Duration type: fixed duration and units
% complete type: Duration
Activity type: Task dependent
Project Calculations:
Recalculate Actual units and cost when duration % changes: Checked
Link Actual to date and actual this period units and costs: Checked
Link Budget and At completion for not started activities : checked
Resource Autocompute Actuals: Checked
Rest all settings are set to default.