Units not getting updated when the Baseline is Assigned and schedule is progressed !

7 replies [Last post]
noufal k r
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 24 Sep 2014
Posts: 5
Groups: None

Hello Planning professionals,

When updating P6 schedule using Duration % complete, Units are not getting updated automatically. This issue exists when maintain & Assign baseline using "save a copy of project as new baseline" option is chosen. However the issue gets solved when I opted for " Convert another project to a new baseline of the current Project" option. Would like to know the root cause of the issue. Please help

Settings I used,

Project Defaults

Duration type: fixed duration and units

% complete type: Duration

Activity type: Task dependent

Project Calculations:

Recalculate Actual units and cost when duration % changes: Checked

Link Actual to date and actual this period units and costs: Checked

Link Budget and At completion for not started activities : checked

Resource Autocompute Actuals: Checked

Rest all settings are set to default.

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you give me your email address I can send you the details that are in a pdf document 

noufal k r
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 24 Sep 2014
Posts: 5
Groups: None

Hi Zoltan,

Thank you for the detailed explanation regarding the application of various percent complete type in real scenarios. It was really helpful. 

noufal k r
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 24 Sep 2014
Posts: 5
Groups: None

Hi Raymund,

Refreshing didnt work. However when I closed the schedule and reopened , it started working. Thank you for your feedback.

noufal k r
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 24 Sep 2014
Posts: 5
Groups: None

Hi Alex,

It worked when I closed the schedule and re-opened. Thank you for sharing your valuable experience.

Raymund de Laza
User offline. Last seen 12 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762
It may need a refresh. Press F5. The database did not update immediately.
Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

The activity percent complete type is one of "Duration", "Units", or "Physical". The percent complete type controls whether the Activity % Complete is tied to the Duration % Complete, the Units % Complete, or the Physical % Complete for the activity. Set the percent complete type to "Duration" for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to "Physical" for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to "Units" for activities which are work effort driven, for example, providing a consulting service.

so your % complete type should be physical % complete

also The Duration % of Planned is defined as The activity actual duration percent of planned. Computed as (Actual Duration / BL Duration) * 100. The value can exceed 100. The BL Duration is the activity's at complete duration from the current baseline.

this i why it is working when you attach a basleine.