Transferring P6 8.4 standalone to new pc

4 replies [Last post]
Peter Holroyd
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 6 Jun 2005
Posts: 167
Any tips on how I transfer P6 software running under windows 7 to a PC under windows 10? Thanks

Replies

Zoltan Palffy
User offline. Last seen 27 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

sent you via email detailed instructions

Peter Holroyd
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 6 Jun 2005
Posts: 167
Ok with data. What I can see is all backed up. What about the baselines which I can't see? Do I have to restore them? What about the P6 software? Email is peterholroyd207@aol.com Thanks
Zoltan Palffy
User offline. Last seen 27 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

1. always back up your data

2. 1st option is to use the backup in sql and copy to a external drive or a network drive.

then on the new pc go into slq and select restore from the external thumb drive or netwrok drive.

3. other option is to open ALL projects and export them as an xer file to a external thumb drive or network drive

if you give me your email address I have detailed instructions on the backup and restore function in sql