Opening 3 projects and create a baseline of them all

5 replies [Last post]
Ron Beechey
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 13 Apr 2016
Posts: 28
Groups: None

How do I create a single baseline of the 3 projects that reflect the 3 open together?   Is it a baseline for each project and just update it or can I do it all at once while they are all open?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can show 3 baselines and the current schedule at the same time

when you select the bars just make sure to put the 3 different baselines on different row numbers so that if the dates over lap one bar is not drawn on top of the other. 

Ron Beechey
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 13 Apr 2016
Posts: 28
Groups: None

Thanks all for the help I think I understand the issue now.  I will have to work around the fact that I really can't show all the baselines at once.   I was mainly interested in major milestones committed to by the contractors and having the ability to show the slippage and the downstream effect while having them as stand-alone plans that I just import into to update.

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can have up to 3 different baselines associated with one project. 

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

when you assign a baseline the project can not be open and once it is assigned it wil become hidden from view until your restore it if you decided to do so.