Creating the baseline in P6

1 reply [Last post]
Miguel Rios
User offline. Last seen 11 years 1 week ago. Offline
Joined: 10 Oct 2009
Posts: 18
Groups: None
How do you create a baseline in P6? I know the approach is different from P3 in which you create a target a file and then make a separate file for your current schedule.

Replies

Dieter Wambach
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Step1: Project --> Maintain BL --> Add ...
Step2: Project --> Assign BL

Read the manual for the difference between Project- and User BL

Good luck!
Dieter