Resource Budgeted Units

2 replies [Last post]
adab azeez
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Greeting to all. Whenever I am adding a new resource to any activity in p6, the budgete units of all previously added resources are automatically changing. It drives me really crazy to put recorrect the budgeted value again and again.Can anyone advice why it is happening and how to prevent. Thanks in advance.

Replies

adab azeez
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Thank you so much david
David Kelly
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Under Edit, User Preferences, Calculations:

Chose "preserve" rather than "recalculate"