Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Properly set up in p6 8.3 tracking Planned vs Actual in Units?

1 reply [Last post]
keith jack
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 8 Feb 2017
Posts: 4
Groups: None

Ladies and Gentleman What in Your opinion is the BEST way to set up in P6 8.3 Schedule to track planned vs actual units? what would be the best way to do it in steps?

 

 

Thank You in advance!!!!!!!!!!!

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Go to the resource directory and create a new resource and call it lumpsum make the type labor. When you make it make sure that calculates costs from units is set to NO.

 

Go to the activities directory and filter for all of the activities that you want the resource on. Then select all of the activities by highlighting them.

Right click and select assign and then select resources and select the resource that you just created called LUMPSUM

This will make the budgeted units equal to whatever the duration is times 8.

Go to file export and select xls then select resource and resource assignments. When you get to the Select Template select add. In the column tab expand the left side under available and expand the Units category and select Budgeted Units and take that to the right side.

Click on the filter tab select add and create a new filter

Where resource id name equal LUMPSUM

Select next and export the units to excel

Open excel and look at the TASKRSRC tab at the bottom and look for the column labeled as target_qty Budgeted Units(h)

Populate this column with the appropriate units and then save the file in excel.

In P6 go to the Projects Directory and make sure that your project is highlighted click on the Resources tab and make sure that in the lower right under RESOURCE ASSIGNMNETS that Resources can be assigned to the same activity more than once is NOT checked.

Now got to the calculations tab and make sure that under Resource Assignments that when updating actual units or costs that Subtract Actual from At Completion IS CHECKED.

Also make sure that Recalculate Actual Units costs and Costs when duration % complete changes IS CHECKED

Also make sure that Link Actual and Actual This Period Units and Cost IS CHECKED

Next go to the Activities Directory and select file import and select xls. File the excel file that you saved and when you get to the Import Type screen ONLY CHOOSE RESOURCE ASSIGNMENTS and import the excel file.

Import the units from excel to P6

Update the schedule with actual starts, actual finish dates and remaining durations. If you update the schedule using duration % complete your actual units will update automatically. If you use Physical % then after you are done updating go to Tools Global change select add

Where Physical % Complete is greater than 0

Then Duration % complete = Physical % Complete

Then on the right select Change then on the bottom select commit changes

 

After you are finished with the update copy the schedule before you do your next update

The first thing that you want to do prior to updating is go to tools Store Period Performance and store the actuals before updating the next period.

Repeat the updating process for the next update