Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual Units vs Actual Regular Units?

No replies
Hamza BENOUFIR
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 22 Jan 2020
Posts: 18
Groups: None

Hello,

What is the difference between Actual Units vs Actual Regular Units. This is the first time I stumble upon Actual Regular Units and I'm unsure what it means. The hint feature isn't very helpful and neither does Google.

When I apply actual units on activity level, I usually just calculate earned units and apply them as cost and real actual hours/costs is managed separately from P6. Would the difference change between a case where the true actuals are applied in P6 and the case where only the earned are applied as actuals?

Thanks,

Renzo Constenla B...
User offline. Last seen 6 weeks 1 day ago. Offline
Joined: 23 Mar 2011
Posts: 21

Hi:

for the software Primavera, actual regular units (for labor resource, as m-h) correspond to non-overtime worked. 

Actual units include the overtime units.

Useful to differentiate for costs purposes (it possible to limit the regular units and set a different price -factor- for overtime).

 

regards