Open a program in p6.4 with a release p6.3

1 reply [Last post]
Ant Pir
User offline. Last seen 3 years 12 weeks ago. Offline
Joined: 17 Jun 2013
Posts: 11
Groups: None

Hi,

Somone kow the procedure how open a program saved p6.4  with  a release p6.3

Regards

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to windows explorer

highlight the xer file 

right click and select open with then choose note pad or word pad

in the first line of the file chnage the numbers from 6.4 to 6.3

save file

import file