Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why Finish Date and Successor Start Date of Activities are same ???

2 replies [Last post]
Muhammad Bilal
User offline. Last seen 5 years 11 weeks ago. Offline
Joined: 9 Apr 2015
Posts: 14
Groups: None

Dear Sir,

I have 1 Issue regarding calendar. I have made 5 Days/week calendar with hours 08 to 16:00. when assigned to Activities, the Finish dates of activities and start date of its successor are same means successor is not starting in new day.... However, i made changes in scheduling option relationship lag to 24 Hours calendar as well... here is the attached picture...
Kindly help me out this situation.
Thanks

4514
waqar.jpg

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

what is the TIME on your data date it should be 8:00 am

yalçın güner
User offline. Last seen 50 weeks 2 days ago. Offline
Joined: 9 May 2015
Posts: 16

You should check your activity's start and finish date time. Most probably your precedessor activity's finish time is same the successor's start time like that ( Predecessor's finish 01-Nov-16 0:00:00 AM Successor's start 1-Nov-16 0:00:00 AM)

 

To fix this go edit menu and user preferences/date tab and check the 24 hour box then you ll see date time linked activities.