Planned Value - Calculated from Baseline Schedule

2 replies [Last post]
Karim Shaheen
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 30 Mar 2014
Posts: 6
Groups: None

Dear All,

  Introduction:

We are preparing for a revised program (Rev.2), the baseline program (Rev.1) already having in-progress activities and will be considered as a baseline for Rev.2 program. The planned dates and planned values to be calculated from the baseline program (Rev.1). So Rev.1 program is assigned as a baseline inside Rev.2 program

 

 Problem:

When I show the Planned Value colum, I am getting a wrong planned value which is based on the planned dates of Rev.1 program while it is supposed to be equal to the Remaining Cost + Actual Cost of Rev.1 program.

Solution Tried:

I have reset the planned dates of Rev.1 program to set it as a baseline for its-self. Unfortunatelly, this is impacting the %complete or the Actual Cost.

 

Anyone can help on that to get correct Planned value directly from Rev.2 program (with assigned baseline: Rev.1 program)

 

Regards,

Karim Shaheen

Replies

Karim Shaheen
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 30 Mar 2014
Posts: 6
Groups: None

Thanks, yes it is really good solution but when I did it, the %complete have been affected. If I corrected the %complete again the current dates won't match the planned dates. It is like closed loop process.

Raymund de Laza
User offline. Last seen 2 days 10 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762
In Rev 1 prior to save as Rev 2 set planned dates=current dates. After doing so save as Rev 2. Then proceed.