Dear All,
Introduction:
We are preparing for a revised program (Rev.2), the baseline program (Rev.1) already having in-progress activities and will be considered as a baseline for Rev.2 program. The planned dates and planned values to be calculated from the baseline program (Rev.1). So Rev.1 program is assigned as a baseline inside Rev.2 program
Problem:
When I show the Planned Value colum, I am getting a wrong planned value which is based on the planned dates of Rev.1 program while it is supposed to be equal to the Remaining Cost + Actual Cost of Rev.1 program.
Solution Tried:
I have reset the planned dates of Rev.1 program to set it as a baseline for its-self. Unfortunatelly, this is impacting the %complete or the Actual Cost.
Anyone can help on that to get correct Planned value directly from Rev.2 program (with assigned baseline: Rev.1 program)
Regards,
Karim Shaheen
Replies