Problem with importing update to the baseline.

2 replies [Last post]
ahmed samir
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 15 Mar 2016
Posts: 2
Groups: None

hey there,

i face a problem while i'm importing update to the baseline, the progress percentage for all activities wasn't the same in site so i changed all Performance % Complete, Start date and Finish date for all activities, there were some activities in the site completed and in the Xer file is still have % or with Zero %...and some activties percentages got increased and some got decreased...

when i prepared the Excel sheet and import it to baseline to re-update everything from the begining, the baseline didn't change and everything still Zero.
 

anyone have a solution for this problem ??

 

Regards, 

Replies

Muhammad Bilal
User offline. Last seen 5 years 6 weeks ago. Offline
Joined: 9 Apr 2015
Posts: 14
Groups: None
All Members Good Day. I am facing one problem which is i made Rev-05 of my In-Progress Project in which i added one Activity given Relationships to some other activities. I made the Rev-05 by Restoring the Baseline. Now when i assigned this Latest Baseline to Updated Progressed Schedule, the added new Activity is not shown. Please let me help out. How can i Show effectively the added activity in the new baseline with Actual Progress Schedule.Thanks
Zoltan Palffy
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that your duraiton type is fixed duration & units/time

run a global change 

where performance % complete is not equal to 0

then

duration % complete equals performance % complete

and importing for progress MUST have start TIMES for activities with actual starts and must have start and fnish TIMES for activities with actual starts and finishes