Assigning resources from BL to update

4 replies [Last post]
mohamed abdalgawad
User offline. Last seen 7 years 43 weeks ago. Offline
Joined: 10 Nov 2011
Posts: 7
Groups: None

Dear All

I finished base line 

Then i made update, all this without assigning resources.

Then consultant asked me to assign resources, I did for the baseline.

now there is a way to make update again to resources BL , but because

I changed many relationships I want to know if there a way to move assignments from the BL to the update ?

Thanks in advance

 

Replies

Abilash Palakkada...
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
The whole current schedule can be updated to BL by update the baseline option. But I prefer not to do that. If i was there at your situation i will set the current file as a new baseline and assign this new BL to current schedule to monitor furthed. If required i will be available on 00971563911927
mohamed abdalgawad
User offline. Last seen 7 years 43 weeks ago. Offline
Joined: 10 Nov 2011
Posts: 7
Groups: None

Thanks very much for response but may be i didn't make myself clear;

I will ask anothe question:

can i import relationships from update to BL ?

Abilash Palakkada...
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Please do following steps Make a copy of baseline file Restore that baseline copy file Import the resource assigments into the restored file Assign this file back as the baseline By Abilash
Abilash Palakkada...
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Please do following steps 1. Make a copy of baseline file 2. Restore that baseline copy file 3. Import the resource assigments into the restored file 4. Assign this file back as the baseline By Abilash