I am currently having issues with the value that is displayed in the BL1 Total Float column.
I can snap a baseline of the current project and this column will show a different value of than what the live project file shows.
For example : Activity has float of -68 days in the current project (which is the correct float). I assign the current project as a a baseline and add the BL1 Total Float column. This column displays -210 days of float.
Any ideas what may be causing this problem. I do not think it is any logic issues because the open project is calculating the float correctly. It is only to incorrect on the assigned baselines.
This is also true if I assign another project as a baseline. If the project is opened alone, the correct float is displayed, once assigned as a baseline, the same issue happens.
Thanks,
Kyle Colcher