Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual units & EV did not update!!

7 replies [Last post]
X Planner
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None

Dear All, 

 

   After updating my program i found the earned value and the actual units for "some" activities equal to zero ( didnot update), 

so i had to fix it manually on excel and import on p6, i'm usining duration %.

Any idea what could be the reason? and how to fix?

Thanks.

Replies

Zoltan Palffy
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

no problem

X Planner
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None

Thanks Zoltan

Zoltan Palffy
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the reason is that you are using duration % complete NOT physcial % complete

X Planner
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None

Thanx Zoltan, I just wanted to know why it doesn't show any values. (the explaination)

Zoltan Palffy
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

to do what  ?

Mehmet Akif İbrah...
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 14 Sep 2015
Posts: 5
Groups: None

Hi,

 

You can write your data in UDF coulomn, after you import P6. And then Use Global change. 

Zoltan Palffy
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

use physical % complete