Milestone Points on Gantt Chart

1 reply [Last post]
Adam Collins
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 24 Jan 2012
Posts: 3
Groups: None

Hello 

I am wanting to set marker points/milestones along the activity line for procurement wysiwyg_imageupload::for a high level tender schedule in P6. I have done this before some time ago using dates in the user defined fields to capture the dates (ie: Bid Submission / PO Award / Delivery). 

Has anyone else done this before and can offer some assistance? 

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

why not create a unique code for the activities that you want to show then assign the code value to each of theses activities then filter for that code