Some activities bar color not seen in Gantt chart??

3 replies [Last post]
Luis Gonzales
User offline. Last seen 12 years 3 weeks ago. Offline
Joined: 22 Sep 2008
Posts: 14
hallo every one..

I am new user of P6..can anyone here help me how to solve my problem..my problem is some remaining works activities bar color(Green) on the gantt chart are not reflected/seen? but most of the activities are seen?


thanks in advance...

Replies

FAHEEM FAIZ
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 29 Sep 2011
Posts: 3
Groups: None

HOW TO CHANGE THE COLOR OF STANDARD NONWORK EXCEPTION IN CALENDAR IN PRIMAVERA P6

Luis Gonzales
User offline. Last seen 12 years 3 weeks ago. Offline
Joined: 22 Sep 2008
Posts: 14
Thanks sir Rodel,

I’ve change already the time scale to week/day,but still not seen the bar color(green/remaining work)on the gantt chart for that particular activities..the only color reflected on that activities are the baseline(yellow) and the Actual works(blue)..
sir if its okay with you,can I email to you the file so that you can view it..I tried to attach here the spot view of that activities with the gantt chart but I dont know how to do it..

thanks

Luis
Rodel Marasigan
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Luis,

WELCOME TO PLANNING PLANNET!!!

Is it a timescale problem or zero duration left but not completed?
If timescale problem then change the timescale from ??? (i.e. year/months) to week/day
Right click on Gantt chart area and select time scale then change Date interval to Week/Day