Display Activity Code values in schedule only, not "empty" bands

2 replies [Last post]
David Ball
User offline. Last seen 5 years 36 weeks ago. Offline
Joined: 8 Aug 2007
Posts: 16

Hi,

I have 5 Activity Codes assigned to the activities in my schedule and these are all included in the Group By column of the Group and Sort window. The last Code is “Discipline” and one of it values is “Cable”.

Within the Cable node in the schedule I want to have a further level with values of “Install”, “Terminate” and “Test”.

The problem I have is that when I create the new code, “Phase”, and assign these codes to the cable activities and include the new code in the Group By column of Group and Sort I get “No Phase” displayed within every node, except “Cable”, which has the headings Install, Terminate and Test, as expected.

I have checked the “Hide if Empty” box in Group and Sort but still get the same thing.

Is there any way to show this new code for Cable only?

 

Thanks very much

 

Dave

Replies

Gary Whitehead
User offline. Last seen 5 years 47 weeks ago. Offline

Rather than using a new phase code, I think you're probably best of adding install, terminate & test as 3 new values in the discipline code, indented to be children of the existing cable value.

Make sure you also indent the discipline code in your group & sort settings

 

 

    
Raymund de Laza
User offline. Last seen 22 weeks 15 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

Create a Filter such as the Code is equal to Phase.