Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Labour units problem while converting form P3 to P6

1 reply [Last post]
Muhammad Imran
User offline. Last seen 9 years 3 weeks ago. Offline
Joined: 19 Sep 2013
Posts: 6
Groups: GPC Qatar

Dear all,

While converting P3 file to P6, a problem is faced that Manhours assigned to activities as Labour unit in P3 formate becomes Non labour units after convertion to P6, which crearts problem in calculation of Project Progress/Level-1 Summary as well.

 

Kindly help me in this regard.

 

Replies

Zoltan Palffy
User offline. Last seen 21 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I have never seen this