Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Weighted duration% complete in P6

1 reply [Last post]
Anbin Ponnith
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158

Dear All,

 

How do I get weighted duration % complete in P6

 

Regards,

Anbin

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

your duration must be based something manhours cost whatever it may be 

so if you have 100 manhours for an activity and you have 50 manhours remaining your weighted duration % complete is 50%