Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Duration changing with resource changes

1 reply [Last post]
Tom Tom
User offline. Last seen 6 years 35 weeks ago. Offline
Joined: 17 Aug 2014
Posts: 31
Groups: None

Hello All,

     I am having trouble with my project duration changing everytime I change the max units/time of a rersource. What am  I doing wrong. I dont not want a resource to recalculate any of my durations.

Thanks

Replies

Zoltan Palffy
User offline. Last seen 19 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to your project directory

make sure that your project is highlighted and open

look at the defaults setting look at the duration type change it to fixed duration & units. Now when you add new activites the resource will not drive the duraitons.

now you have to fix the duraiton type for the existing activities

go to activities add column

look under General and add Duration Type

change the top one to fixed duration & units then do a fill down for the remainder of the activities

this should fix it.