Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

activity usage profile - Need to Show Values

3 replies [Last post]
Premod Jacob
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 16 Nov 2013
Posts: 3
Groups: None

Hi,

Good Day !!

 

Is sit possible to show the unit values at the top of each bars in Activity Usage Profile Histogram in P6..?

Replies

Raymund de Laza
User offline. Last seen 32 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

That's not possible. Suggest to Transfer the Data to Excel.

Premod Jacob
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 16 Nov 2013
Posts: 3
Groups: None

Hi De Laza,

I want that labels / values in the Acivity Usage Profile Histogram, not in Ghant Chart.

Is there any option to give a label / unit in that Histogram printout ?

Raymund de Laza
User offline. Last seen 32 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Jacob,

Use the Bar Labels.