Hi,
I am having problems updating a baseline in P6 and I need it completed urgently!!
I have a project, which has links to other projects and it is currently baselined. It has been recognised that some Engineering activities within the project were incorrect at the time of baselining and customer has given permission for certain activities in the schedule to be rebaselined (not all activities).
To do this I restored the baseline, made a copy and reimported the copy to the project as a baseline in order to keep the original baseline as well. I then used the copied baseline and used the update function. I created a filter for the activities I want to update and clicked update but the dates are not matching the current dates.
Can anyone advise why this isnt working?? Im tearing my hair out here, I dont know whether I am doing something wrong or whether it is just P6 not working??
Many thanks in advance of your reply.
Replies