Oracle Primavera - PM6 Please also ensure that the Please also ensure that the drive activity dates is checked on and the lags are 0 for your resource assignment: One more reason could be One more reason could be that, there are activities with negative float which is because of unsatifactory constraints attached to activities in the network. Remove the constraints to the activities connected with the activity's network path. Stephen,I suggest to Stephen, I suggest to investigate the Calendar assigned with the Resources. View the Start and Finish date of the Primary Resource. Hope this will help. Log in or register to post comments
Please also ensure that the Please also ensure that the drive activity dates is checked on and the lags are 0 for your resource assignment:
One more reason could be One more reason could be that, there are activities with negative float which is because of unsatifactory constraints attached to activities in the network. Remove the constraints to the activities connected with the activity's network path.
Stephen,I suggest to Stephen, I suggest to investigate the Calendar assigned with the Resources. View the Start and Finish date of the Primary Resource. Hope this will help.
Please also ensure that the
Please also ensure that the drive activity dates is checked on and the lags are 0 for your resource assignment:
One more reason could be
One more reason could be that, there are activities with negative float which is because of unsatifactory constraints attached to activities in the network. Remove the constraints to the activities connected with the activity's network path.
Stephen,I suggest to
Stephen,
I suggest to investigate the Calendar assigned with the Resources. View the Start and Finish date of the Primary Resource.
Hope this will help.