Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Bucket planning

2 replies [Last post]
Bichu C C
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 28 Jan 2013
Posts: 3
Groups: None

Dearss..

How to enable bucket planning in p6 to enable to enter budgeted units manually.

Replies

V Kutty
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 17 Jan 2011
Posts: 23
Groups: None

HI,

Is there a means of stopping P6 from re allocating resources based on the total resources if the activity is delayed.

Thanks,

Abilash Palakkada...
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47

just go to resource usage spread sheet and selct the activity, then u will be able to do bucket planning