Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Limit Layout to EPS Node

1 reply [Last post]
Hugh McLeay
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 12 Mar 2012
Posts: 20
Groups: None

Hello,

I'm just wondering if there's a way to limit access to certain layouts when working on a project in a particular EPS node.
E.g. I have different EPS Nodes for Client programmes, My programmes, and Subbie programes.
I also have different layouts (specifically different title blocks and logos for printing).

I'd like to make it so that I can't accidentally apply a Subbie layout to a Client programme and hence print it with incorrect title block and logos etc.

Thanks,

Hugh.

Replies

mimoune djouallah
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

Hugh

i avoid this situation by adding a prefix to the global layout for example:

Client1- three weeks look ahead

Client 2- three weeks look ahead etc

it would be nice if  we can group  layouts by EPS

 

regards

mimoune