Task mode in activity Zero

1 reply [Last post]
Alex Lyaschenko
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

Hi Helpers,

Is it a way to change TASK MODE for activity ZERO (Project summary)?

 

Regards,

Alex Lyaschenko 

Replies

Alex Lyaschenko
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 15 Aug 2011
Posts: 59
Groups: None

wysiwyg_imageupload::

8367
msp_zero_task.png

Rodel Marasigan
User offline. Last seen 1 day 15 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

It is not possible. It always default to Auto and cannot be manuall. It always calculate overall project duration even with no task.