Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Different calender to summary task & Activitis

2 replies [Last post]
mukunda y
User offline. Last seen 11 years 15 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None

I want to assign 6 days calender to the activities & want to calculate the summary task duration based on the 7 days calender,,, is there any way to do this,,,

 

Thanks & Regards

Mukunda

Replies

mukunda y
User offline. Last seen 11 years 15 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None

I got it, Thank you Mike,

Mike Testro
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Mukunda

I don't see why not - just create the two calendars and assign them accoringly.

If MSP won't allow that simple operation then use real software like PowerProject.

Best regards

Mike Testro