Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

where is the switch to make % Complete change Remaining Durations? and vice versa

1 reply [Last post]
Rodney Jones
User offline. Last seen 21 weeks 3 days ago. Offline
Joined: 17 Jun 2012
Posts: 65
Groups: None

Hello All,

where is the switch to make % Complete change Remaining Durations?

 

My Tasks are set as shown below, but the % Complete field seems to be manually entered, how do I get the % Complete to be auto calculated based on Remaining Duration or vice versa?

Replies

Paul Harris
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6.

Regatrds

Paul E Harris

Eastwood Harris Pty Ltd

www.eh.com.au