Anyone know of a formula where I can pick this up and put it in a custom field?
I'm trying to create a view where the final milestone of a summary reflects the Summary % complete
Forum Sponsor
Top Posters
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Have you looked at Copy / Paste Link? One way you could do this is to :
1) Copy the % complete of the summary line you want to track
2) set up a new task which has 0d (i.e. is a mileston)
3) Edit / paste special / paste link into a custome field for that field
This will throw a warning when you open the project that it contains links - always agree to this
I would note that a milestone should always have a binary nature; it should be 0 or 100% complete; the practice of saying that a milestone is 50% complete is to misunderstand the purpose of a milestone but if you're being pushed into a corner and can't educate someone the above will work .
Regards
Miles
Are you tying to create a milestone with a % completion which is the same as it's summary task, or are you trying to create / otherwise manipulate a milestone based on different % completion values from the summary task?
Phil
Hi Stuart,
Please completely re-phrase your question. Your topic heading and your remarks seem to be heading in two opposite directions, so it's impossible to see what you are doing or what you want to do.