Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Calendars ^ _ ^

1 reply [Last post]
Shishir Dhatwalia
User offline. Last seen 6 years 48 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: GPC Qatar

Hi !!

I want to make a calendar in MSP 2013 for which I copied the 24 hrs shift.

Now using exceptions I entered the 4 national holidays which went fine.

I marked all the sundays as Off. Now we have a shift change / off day every 15 days or on  the alternate sundays.

Can I do that using some command or I have to select every alternate sunday manually for the project duration ??

 

 

Replies

Shishir Dhatwalia
User offline. Last seen 6 years 48 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: GPC Qatar

I did it using the exceptions tab

 

made an exception called "Alternate Sunday"

Then click - details; Non-Working radio button is selected &

used the recurrence pattern.

 

If any other method is there plz let me know.