Hi guys,
I am currently working on a RDT project which has a fixed duration of 48 months.
Thats my first project and I am a bit lost :-)
My problem is that I have to calculate everything on a monthly basis (task duration, resource costs). In the calendar options, I see I can determine the number of working days for a month BUT it will remain the same number of days for every month whereas each month has a different number of working days. As a consequence, when I introduce a calendar of 21 days a month, my project starting on the 01/04/04 is ending on 11/02/08 (48 months)whereas it is supposed to finish on 31/03/08.
Is there another way to create a calendar which would take into account the real number of working days of the months that interest me (Jan 04 to Mar 08)?
I hope my explanation is clear because it is a bit complicated to write down.
Thanks for all,
Isabelle
Replies