Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Microsoft Project and Deadlines

No replies
Emily Foster
User offline. Last seen 2 years 25 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Deadlines are a great feature in Microsoft Project. Here's how they work  http://ow.ly/Bgfs302zHP0

Tom Boyle
User offline. Last seen 10 weeks 6 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Emily,

To add to the elementary discussion of your article:

There are two main advantages to using a Deadline instead of a Finish-No-Later-Than constraint in MSP:

  1. The single allowed slot for a task constraint may be used for other purposes;
  2. The logical conflict that accompanies unmet late constraints - (by default, MSP re-schedules the task to meet the constraint date even if it violates logic) - can be avoided without changing the default settings for the project.

In every practical respect, Deadlines in MSP function identically to Finish-on-or-Before constraints in P6.  That is, they override the late-finish dates in the absence of more stringent conditions, and Total Slack is reduced as a consequence.

Unfortunately, your article seems to invite the novice scheduler to use Deadlines willy-nilly without fear of complications, and this is wrong.  Imposing multiple deadlines "throughout the schedule" as you suggest in the final paragraph makes Total Slack completely unreliable as an indicator of the Driving Path to Completion -- of the Project or of any deadlined milestone.  Since MSP defines "Critical" tasks solely based on Total Slack, your novice scheduler may be hard-pressed to accurately describe where the real "Critical Path" is.

For these reasons - and for your mention of "longest path", which is a concept that is distinctly foreign to any out-of-the-box MSP schedule - I would suggest deleting your "Summary" paragraphs and starting over.  In my view, Deadlines in MSP are essentially not a huge advantage - but a patch needed to offset weaknesses in other areas of the tool.

By the way, all of these issues are easily resolved with a 3rd-party add-in that I use, but very few MSP users seem to have access to similar tools.

Rgds, tom