Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

extended deadline marker

2 replies [Last post]
assaf f
User offline. Last seen 10 years 33 weeks ago. Offline
Joined: 26 Dec 2007
Posts: 32
Groups: None
Hi,
Is there an option for the deadline red flag to appear after a defined period of time from the deadline? not at the instant the activity has passed its deadline.

Thanks,
Assaf.

Replies

Trevor Rabey
User offline. Last seen 2 years 4 days ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
I answered this in microsoft.public.project
Make a Milestone (duration = 0).
Make the task a FS predecessor with some positive lag.
Put the deadline on the milestone rather than the task.
Trevor Rabey
User offline. Last seen 2 years 4 days ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
I answered this in microsoft.public.project
Make a Milestone (duration = 0).
Make the task a FS predecessor with some positive lag.
Put the deadline on the milestone rather than the task.