Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Revision of baseline

No replies
gaurav joshi
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 15 Oct 2011
Posts: 4

Residential project of P + 18 with conventional shuttering for RCC work.

When i need to revise the baseline considering the actual dates when my RCC work has completed 50% i.e. 50% RCC slabs casted.

WHen i am revisiong the baseline considering the actual casting dates of slabs, activities changed to non critical, but practically RCC work has to be critical in the schedule isnt it ?

What should be the overall approach while revisiong the baseline considering actual dates & my 70% project is balance approx.

Gaurav