Project BaseLine

5 replies [Last post]
Berli Berli
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 20 Jun 2002
Posts: 19
Guys,
I want to add a baseline to may msproject schedule, can I used a baseline refer from other msproject file or import file for a baseline ? thanks

Rgds,
Berli

Replies

Trevor Rabey
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
If you just want to compare the baseline start and finish from another (older) file with the current start and finish in the newer file you can just copy and paste the baseline start and baseline finish fields from the older and paste them into corresponding fields in the newer file.
This assumes that you still have the same number of tasks in the same arrangement with the same ID numbers in both files, but even if not it is still easy with a bit of help from filters etc.
Berli Berli
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 20 Jun 2002
Posts: 19
I am still use 2003 version. I have already tried your sugestion. thanks
Berli Berli
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 20 Jun 2002
Posts: 19
Alex,
Thanks for your input, so MS.Project can not import a baseline from other file. My problem is I want to compare the current schedule with one of my scenario when developed the schedule. thanks