HELP!
Im four days into my new job and almost done creating a finishes programmes for some refurbishment works on some houses.
Ive put some bare bones together and been to site, made my notes, come back the office to update the project and see what I can juggle about.
In the previous version (2007 I think) if a future activity was due to start, and I made a start on it, when I hit update project, it would bring the remainder of the task forward to the progress line.
For example, I have a bar for "Decorations" 2d long, on the Ground Floor, starting on 26th June. The guys have actually done one of the rooms, so Ive marked this activity as 25% complete. After Ive hit reschedule, the completed and uncompleted parts of the bar stay where they are, on 30th June. I wanted the completed part of the bar to go behind the progress line and the remainder of the works to reschedule to immediately after the progress line.
Anything that HASNT started (links permitting) has been brought forward, its just items that have had a start on them causing this problem.
I hope this makes sense? If someone can help me ASAP I'd be very grateful, else my job is going to be a nightmare rescheduling everything by eye.