Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

how can define a task that last from start of project to finish of project??

5 replies [Last post]
Shima Zabetian
User offline. Last seen 2 years 35 weeks ago. Offline
Joined: 25 Mar 2011
Posts: 18

Hi, guys

I'm not good at MSP software.

how can define a task that last from start of project to finish of project??

I know that in p6, we can change the activity type to Level Of Effort, but What about MSP, how can I define this activity??

 

regards

Shima

Replies

Tom Boyle
User offline. Last seen 11 weeks 6 hours ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

The paste-links seem a bit more robust in newer versions than they were in 2003, but it's still a patchwork approach.  Past experience mostly cured me of my desire for hammocks in MSP.  Now on the few occasions I can't do without, I use alternate methods that don't give me a big headache....

http://www.boyleprojectconsulting.com/TomsBlog/2017/09/26/an-alternate-approach-to-hammocks-in-microsoft-project/

David Manna
User offline. Last seen 6 years 45 weeks ago. Offline
Joined: 26 Nov 2017
Posts: 13
Groups: None

I agree with Mike. This sounds like the best solution. I am still learning to use MSP and this forum will definitely help. 

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

1) Set up & logically link normal start & finish milestones for the start and finish of your project.

2) Copy the Start field of your start milestone, then right click on the start field of your "level of effort" task, choose paste special > paste link

3) Do the same with the finish date from your finish milestone

4) Put something in the notes column explaining what you did, as the start & finish milestones won't register as predecessors of the "level of effort" task

 

 

This is For MSP 2003. There may be a cleaner way in later versions.

 

Mike Testro
User offline. Last seen 36 weeks 15 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Shima

Create a summary bar over all the tasks and label it your task long activity.

Best regards

Mike Testro