Total slack

3 replies [Last post]
Deepak Gowda
User offline. Last seen 13 years 1 day ago. Offline
Joined: 13 Jun 2011
Posts: 13
Groups: None

Good evening guys,

I have got one question i have scheduled one project in picrosoft project.

start date is : 18.07.2011

End date is 30.08.2011

Relation :FS

i have entered status date as 28.07.2011 and i dint updated any tasks, then i enetred F9 to caleculate mannually , i am not able to see any negative slack of 10 days (or delay of 10 days since i dint started any work) 

if any one has answer please let me know. thanks in advance please note i have tried with must finish contraint too but the resilt is zero

 

 

Replies

Deepak Gowda
User offline. Last seen 13 years 1 day ago. Offline
Joined: 13 Jun 2011
Posts: 13
Groups: None

Spot on!!!!!!!!!!!!! Thank you Rafael

 

Cheeeeeeeeeers

Rafael Davila
User offline. Last seen 1 week 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230

Make sure you set a must finish project date constraint if you want to compute float relative to such date. It can create negative float or even a longest path with positive float.

If you do not set a finish date constraint no negative float will be computed and float will be zero along longest path.

Deepak Gowda
User offline. Last seen 13 years 1 day ago. Offline
Joined: 13 Jun 2011
Posts: 13
Groups: None

sorry its microsoft project cheeeeeeers