Total Slack

2 replies [Last post]
Stuart Atkinson
User offline. Last seen 1 year 23 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Gents,

Why am I getting Total Slack values of 49.56, why are they not whole numbers. I am sure it will be calendar or workday related. Can someone please explain the fix. P.S.Using MSP 2007.

Thanks,

Stuart

Replies

Stuart Atkinson
User offline. Last seen 1 year 23 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Thanks Darren,

I will investigate
Darren Kosa
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 256
Groups: None
Hi Stuart,

I don’t use 2k7, but I’ve experienced similar problems in 2k3.

Most of them have been down to work / units driving the durations or split tasks affecting the start times of successors.

Try changing the date format to include hh/mm and then looking at the Start / Finish dates to see if anything stands out.

My default Start / Finish times are 08:00 and 17:00 so if I now see a Start or Finish that doesn’t fit in with that (excluding half days), then I’m pretty sure something is amiss.

Regards,

Darren