move complex set of tasks/subtasks without losing the structured numbering

Member for

21 years 7 months

Copy the relative numbering you want to keep into a user defined field. Then you will be able to use the field to organize and sort.

If in the future you add activities use two decimal places to locate as much as 100 new activities between any whole number in the sequence that best fit your needs.

The problem with this method is that it allows for duplicates, using WBS does not. On the other hand it allows you to keep different relative numbering sets.

How do you prevent duplicates in MSP? I do not know.

How do you filter for duplicates in MSP? I do not know.

In addition to WBS you shall explore outline codes.

Member for

14 years 3 months

No Mukunda,

I have an old long and complex plan.  I have inserted at the top a new set of phase-names and top level tasks and second level tasks.  I need to cut the whole of an old discovery phase and paste it in a few tasks and off sets down, but I need the old part to auto-renumber according to the postion at which i paste it in.

Dave     

Member for

16 years 11 months

Dave 

u mean u wan to keep the activity id same... if so it is not possible in MSP.

 

Mukunda