I need to copy/move a complext set of tasks & sub task (many levels) under newly added task without losing the relative structured numbering. Can't find it in the manuals.
I have Proj 2007. I have been given a 1,000+ row plan, and need to move various chunks of the long plan into (under) new phase/task/subtasks. When I expand all levels I had hoped to select all and paste them in to a blank set of rows, but I can't get the relative numbeing to be maintained. My alternative is to print out the whole 1000 lines (done that) copy (and lose the numbering) and then correct the numbering offsets based on the print out (tedious, don't want to do that).
There must be a better way!