Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Strengths & Weaknessses of Ms Project & Primavera P6

5 replies [Last post]
John Banks
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 28 Jun 2007
Posts: 35

Does anyone know of an article or document discussing the above?

Replies

Mike Testro
User offline. Last seen 30 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Mark

You forgot Asta PowerProject and Spider - both far superior to P6.

I am also recognising some repetion in your threads promoting "Path Approximator"

Is this some sort of commercial pitch?

If so please refer to Clause 10 in PP rules.

Best regards

Mike Testro - Forum Moderator

Mark Greenhalgh
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 21 Jul 2003
Posts: 13

 

Basics are the most important thing: to use what you are most comfortable with, but you should own them all:  MSP, ST, and P3 on old 32bit computers but most importantly you must own P6 v8.1 Professional on a 64bit computer and then you can convert anything to anything.  Have you tried Longest Path Approximator?  http://scheduling.spacetechnology.net  It is capable of moving the data date back to the beginning of the month, and then you can see the critical path.  Hint:  Ask for  a free sample!
Tony Virkamaki
User offline. Last seen 12 years 16 weeks ago. Offline
Joined: 7 Aug 2009
Posts: 8

Hi John, iqbal, Daniel...

MSP by itself does not have the capability for enterprise-wide multiple project work without a considerable amount of custom programming, however, MS Project Server + MS Project certainly does. The existence of two related programs allows companies to select the level of financial commitment.

P3 has had an add-on VBA driver available for some time. It's quite likely that most schedulers are unaware of the existence of said driver. I have personally never met another scheduler who was aware of the existence of the driver nor who knew how to use it. P6 appears to have VBA more seamlessly integrated into the user experience.

In any case, both programs are now at the stage where using VBA allows programming a correction of almost any lack in features or weakness. What either program lacks in ease of use or reporting (or whatever) can be programmed via DDE in VBA.

The result is that if you wish to control either MSP or Primavera from Excel, Access, Word or even Outlook, those programs can supply missing functionality. (I wouldn't recommend Word unless you are planning to write a book, however it is doable). Personally, receiving progress updates in Outlook and having Primavera/Project automatically update is a real timesaver especially when the progress submitters are neither scheduling experts nor computer experts.

Also, it is significantly less expensive to have a typist entering progress data into an Excel spreadsheet which in turn updates the schedule than to type it in yourself (assuming a difference in pay in favour of the scheduler or planner).

Ultimately, VBA allows programming such that some people can use Primavera and others can use Project for the same project at the same time with both being up-to date while seamlessly reporting in Excel and sending automated notifications and/or requests for schedule updates via Outlook. Furthermore, having Excel run a Monte Carlo-type risk analysis in the background while this is all going on is quite handy as well.

 

In conclusion, neither program is better/stronger than the other if all program features are fully utilized. However, the less actual skill (not experience, since many have plenty of experience but little skill) a user has with either program, the more significant the perceived differences become. Add to that the fact that a very large number of users learn the use of any program in the most difficult manner possible (e.g. by not reading the manual, among other things) and a significant amount of resistance to the use of another program is generated. Net result: sloganeering along the lines of "Program A is much better/has feature X/etc."

The greatest weaknesses are almost always between the ears of the users of the programs.

iqbal
User offline. Last seen 13 years 21 weeks ago. Offline
Joined: 27 Sep 2010
Posts: 3
Groups: None

Hi All  What MS project and P6 do not have

 

1- MS Project had a computed columns where p6. upto ver 7 do not have

2- MS Project had a programming language where p6. upto ver 7 do not have

3-MS project is ( understandably ) more flexible in importing and exporting with mircosfot office packages and in specificlly excel. P6 had limited Excel importing and exporting

Daniel Limson
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi John,

I think as planners, we can evaluate both softwares, so let me start and hope we can have a good comparison and intelligently decide which sofware is right for our project.

1.) P6 is capable of handling multiple project enterprise wide. MSP does not have this capability

2.)