Hey guys I am working on MS Project 2007
I'm setting up a large scale project and the resources aren't allocated at a granular level yet. I'm making broad sweeps to determine who and when I'm hiring by setting up "team" resources. The lead for each team is at 50% capacity because of other duties - so in a team of 7 people the resource is set to a max of 650%
When it comes to levelling all tasks - project doesn't seem to want to account for that extra 50% so it's useless to me.
I've tried several methods and still can't find a solution so I thought I'd post it. I simplified a test project to test different ideas and still can't work it.
Test project:
2 tasks at 5 days each
1 Resource set at 150%
Desired outcome:
I'd like project to level the first task at 100% and the second task at 50% I'm starting to think it's not possible?
Tried:
- changed Task type to all options
- Reset everything and tried reassigning the resource - works when I set the resource to 50% but not when i set it to 150%
- changed levelling options - pretty much tried everything, levelling per hour, creating splits etc
- Input work days instead of duration and vice versa
- Set up 2 resources - one at 100% and the lead at 50% on the same task but can't get it to level either (changing to all task type options & also
Thanks!
Debossaurus
Replies