How i can combine 2 or more projects y Microsoft Proj?

3 replies [Last post]
Jhorbam Baena Orozco
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Hi, I have 4 projects, that in the start where visualized in individual way...but in this moments i need to combine this projects to obtain a unique general S curve of development...Can someone tellme how i can do that?...and how i can avoid problems in the process?

Thanks

Replies

Jhorbam Baena Orozco
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Hey Fellas...a lot of thanks for the help....

Thanks again
John Banks
User offline. Last seen 5 years 25 weeks ago. Offline
Joined: 28 Jun 2007
Posts: 35
Insert each project into a new master project. Update the projects separately, report out of the master. If the four projects share common resources, remember to point the master project to the shared resource pool.
Rodel Marasigan
User offline. Last seen 6 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Jhorban,
You can use Insert Project and still can track project separately and update. This process will combine all projects and keep updated while tracking separately.

You can also use copy and paste method. This will combine projects but not track separately.