Project Calendar

2 replies [Last post]
richu rose
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 13 Feb 2007
Posts: 63
Groups: None
Hi,

How to make a project calendar into global, so that it is avilable by default for every new project created.

Cheers,
Richu

Replies

Trevor Rabey
User offline. Last seen 1 year 34 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
When you do this (with Tools, Organizer), make sure that you have first given your new calendar a special name such as "AA Special Calendar 1". Then you will be able to find it at the top of the list and you will be able to distinguish your calendar from the built-in ones.
DON’T just change the Standard Calendar and then put that into the global template.
Darren Kosa
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 256
Groups: None
Hi Richu,

Tools > Organizer > Calendars

Select the project calendar(s) from the views available in your project file and left-click on the ’<< Copy’ button to copy into the Global.MPT.

Regards,

Darren