I am using a schedule created in P3.1 and it has been converted to MS Project 2000; this is by request of the owner and is not negotiable. Tasks that have FS link with its predecessor. My data date is 3/1/08, so no incomplete tasks appear before that date. Here is my problem: Task A starts and finishes 3/2/08, but its successor is starting on 3/2/08; this is not a FS relationship. My Resource and Task calendars are identical and follow the 5 Day work week with an 8 hour shifts per day. I tried to set the constraint type to Start As soon as possible, but it makes incomplete tasks occur before the Data Date.
It is not a true resource loaded schedule. What I mean is that the Resource, a sub-contractor, may be assigned to more than one task occurring at the same time. This is fine.
What is my problem? BTW, I hate MS Project. You guys are the smart ones.
Replies