Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Changing Date ..Man Hours Change

2 replies [Last post]
zulfi Ali
User offline. Last seen 18 years 11 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 17
Hi Friends, I

I have a problem and need your help to fix it ut. I work on P3 but, had to work on MSP.
Whenever I change activity duration and date , activity resource manhours also change, could you please help to fix it up.

Thanks

Replies

zulfi Ali
User offline. Last seen 18 years 11 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 17
Thank you very much Alexandre. Only one activity still showing the same attribute. Let’s see
Once more thanks a lot for your kind information.