Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Calculating Hours-Man with Project

2 replies [Last post]
Jhorbam Baena Orozco
User offline. Last seen 2 years 50 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Hi...with Primavera Project Planner i can get the report of the Hours-man neccesaries to complete the project...but i not found a similar option in Microsoft Project...an option that i can use to get that information calculated by the Microsoft Project...

Can someone tell how i can get that report?...or that option are not able in Microsoft Project?

Thanks

Replies

Rodel Marasigan
User offline. Last seen 1 week 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Jhorbam,
Try View-> Task Usage or View-> Resource Usage. You can insert the column that you want to show like Baseline Work, Work, Remaining Work, Actual Work...etc. You can also apply groupings.
Trevor Rabey
User offline. Last seen 2 years 1 week ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Remaining Work?
See the Work Table.